Welcome to the project page for the Hercules Drive Culvert Replacement Project. In August 2019 the Town of Colchester replaced the culverts that allow Sunnyside Brook to pass underneath Hercules Drive approximately 500 feet from the intersection with Roosevelt Highway / Route 2/7. 

Project construction took approximately two weeks and was completed at "low-flow" per state permitting requirements. 

This project was funded by the Stormwater Utility and had a total project cost of approximately $155,000.